George Harms Construction Company continued work on the replacement of the Raritan River Bridge on a frigid January day as a major winter storm barreled toward New Jersey. This determination, along with a unique decision-making strategy centered on a specific piece of equipment, are keeping this critical infrastructure project on track.
The material under the riverbed largely dictated the need for a rig the size of the BG 55. The upper layers were soft, silty clay underlain by sand layers of varying depth. Beneath that was dense clay and siltstone.
A group of key project executives from Harms and Equipment Corporation of America (ECA) gathered on the shoreline as work progressed and crews secured the barges holding the equipment.
“We can handle cold temperatures and snow but our biggest nemesis out here is the wind,” says Jason Hardell, P.E., Senior Vice President of Operations. “That’s why we all have beards.” The group erupted in laughter.
This 112-year-old bridge carries an active New Jersey Transit line across the river from Perth Amboy to South Amboy. After damage by Superstorm Sandy in 2012, a new span will incorporate structural designs and materials to bolster its defenses against severe weather.
In May 2020, Harms was awarded a contract to install 87 drilled shafts across the Raritan River in configurations of two to 10 shafts per pier. It was the first of three construction phases to replace the bridge with a lift span. This bridge represents the largest project Harms has done in terms of dollar value, but not in scope.
Building the BG 55 into the Bid
The selection of the BG 55 was founded on a 30-plus year business relationship and friendship between ECA New York, New Jersey Regional Sales Manager Bruce Langan and Harms President Emeritus Tom Hardell.
Harms was awarded this project when the original low bidder retracted its bid. No stranger to $200-million-plus bridges, Harms wasted no time mobilizing and starting work in July 2020.
Harms worked with ECA’s Director of Bauer Product Sales and Service Gordian Ulrich to spec the BG 55 into the project during the pre-bid phase. Ulrich’s career started in 2007 at Bauer Maschinen’s method development department in Germany and he has been involved with various drilling applications on a global scale.
The company considered other brands of equipment, but ultimately concluded that only the BG 55 could cost-effectively drill 8-foot-diameter shafts up to 240 feet. “We went out on the limb and purchased it before we were even low,” says President and CEO Rob Harms.
In the Bauer lineup, the company also considered the smaller BG 40, but lacked the winch capacity Harms needed. With the massive Kelly bar, tooling and heavy clay, Harms considered the BG 55 the only choice.
ECA had the rig shipped from Bauer Maschinen in Germany to the Port of Newark and hauled to the Harms waterfront facility in Newark, N.J. Once assembled, the BG 55 crawled onto a 200-foot-long Flexifloat Barge that a crew then floated to the Raritan River Bridge site. This barge would serve as its mobile working platform.
Barge stability was critical with the 118-foot-tall BG 55 mast subjected to heavy winds during drilling. The barge, built of modular Flexifloats, had a unique configuration specifically designed for this project and this application. Its 10-foot-wide sections in 10- and 20-foot lengths snap together like Legos, so Harms had the flexibility to add and remove.
Six hydraulic spuds with 24-inch-diameter pipes anchored the barge to the soft riverbed. Despite the added stability, Harms and ECA had to overcome up and down movement every time the Kelly bar moved.
Harms worked with Flexifloat at the pre-bid stage to design the barge around the BG 55. The polymer slurry tanks on the opposite side served as a counterweight. The hurdle Harms had to overcome was that the weight fluctuated during drilling as the Kelly bar turned and slurry pumped to the BG 55 to support drilling.
“We had to analyze different drilling scenarios, including worst case scenarios,” says Jason Hardell. “Then we calculated the forward- and rear-leaning barge trim, conveyed that to Bauer, and received confirmation that there would be no issue with the machine.”
Drilling in the River
Harms installed rock sockets into the siltstone out in the channel in the deepest part of the river. Some of the shallower shafts socketed into dense clay. The siltstone had tested unconfined compressive strength as high as 7,000 psi.
According to Vice President of Construction Kevin Harms, the BG 55 excelled when drilling in hard materials. He says, “The BG 55 has been good in terms of its performance in harsh geotechnical conditions and overall capabilities.”
Harms did two test shafts in November 2020 using the BG 40. A third test shaft in January 2021 used the larger BG 55. The installation of the production shafts started in February 2021.
The Harms Way
Pre-planning seems to be a recurring theme for Harms. Rob Harms says, “We looked at different options and different ways to do it, and it has paid off. We had some large, difficult challenges to overcome that weren’t in the planning process. That’s when you really see the value of the team.”
“We had some large, difficult challenges to overcome that weren’t in the planning process. That’s when you really see the value of the team.”
– Rob Harms
From the workers in the field that barely pause to make eye contact with visitors, to the project management team, a get-it-done attitude seems to be the norm at Harms. “Our people have the same mindset: We’ve got to get this done no matter what it takes,” says Rob Harms. “When major issues arise, we focus on addressing the problem before considering the cost.”
Harms only buys equipment. Once the contractor is convinced that a certain machine is the right fit for a certain project, it makes the purchase with the conviction that it can keep it busy on future projects. Harms also has a reputation for maintaining equipment, which translates into an above-average resale value. “If you own it, you’re only making money when it’s running,” says Kevin Harms. “If it goes down on a job, we lose money, so making sure it’s serviced and running is crucial.”
Next Level Equipment Support
“It’s a 24-hour operation,” ECA’s Gordian Ulrich says. “If the phone rings in the middle of the night, we need to have boots on the ground immediately to support the customer.”
It was critical to have the right people to assemble the BG 55, start up the project with Harms, conduct operator training and service the equipment. ECA’s team included technicians, operator trainers and even welders for the tooling.
“Projects of this size and scope are what the ECA Bauer Service Team lives for,” Ulrich says. “In 2019 we started building a team of Bauer product specialists to be able to support our customers in the field when it is show time. Our crew set up and commissioned the rig before our in-house operator trainers started working with three Harms operators to ensure safe operation with this massive 84-meter-long Kelly bar together with the biggest rig on the East Coast.”
ECA knows how to control the risk above ground, but once the drill breaks ground, all bets are off. With offshore drilling, no backup rig could be brought in if the BG 55 went down. The movement of the barge was also a factor, especially drilling at depths of up to 240 feet. The timeframe Harms had to drill a shaft was fixed, which added yet another layer of complexity.
Self-Sufficient Drilling Barge
“Everything we need is on that drill barge,” Jason Hardell says. “The whole operation is self-sufficient.”
Harms first pinned a square-shaped casing guide to the BG 55 barge to ensure that the casing was straight and properly located. Sections up to 145 feet were set with a 330-ton crane on a neighboring barge. The drilled shafts were 102-inch diameter from top of casing to the bottom with 96-inch rock sockets, the longest of which was 30 feet.
The BG 55 was not the only massive piece of equipment on site. Harms used a crane-supported 100,000-pound ICE 200C Vibratory Driver/Extractor to drive the casing that will remain in place as part of the structure. The BG 55 would then drill out the material within the casing to the depth Harms required.
The depth of the shafts and the uncased section below the casing presented the greatest complexity for Harms. Polymer slurry was required to keep the hole open in sandy soils between the casing and the rock socket.
The BG 55 was used strictly to excavate material and drill the rock sockets. Its cleanout bucket removed the spoils with the help of polymer slurry pumped from nearby tanks. A floating tank was moved back and forth to supply clean water for the reuse of the polymer slurry. Crews loaded spoils into a hopper barge by excavator for transport to the shoreline for disposal.
Workers spliced the galvanized rebar cages on an adjacent barge. Once completed, the crane hoisted them into the casing. Workers completed the shafts by with the pumping of 4,000-psi self-consolidating concrete (SCC).
Harms also used its Bauer BG 40 for backup. The rig was positioned on a pile-supported trestle to Kelly drill the shallower shafts near the shoreline.
The Trains Kept Rolling
Passenger trains chugging past the Harms barges offered a constant reminder of the challenges of working next to an existing bridge. Drilling 240-foot shafts in proximity to an active railroad requires caution and finesse.
Project specifications required Harms to complete the shaft concrete within 36 hours from when drilling advanced below the permanent casing. “We had to drill it, clean it out, get the rebar in, and fill it as quick as possible,” says Rob Harms. “The potential for collapse increases the longer you leave the hole open so we had to move quick.”
Vibration was also a concern, which spurred project designers to choose drilled shafts over driven piles. Harms installed and monitored vibration sensors on the existing bridge for safe measure.
Harms equipment operators, namely for the BG 55 and crane, had to work carefully to avoid contact with overhead lines on the existing bridge. The wires carried up to 38,000 volts. Working from barges in a windy area further complicated matters.
Transporting, Prepping and Handling Casing
Casing was sourced from Illinois. Fabricators that can produce sections up to 143 feet in length with the ability to roll 1-inch walls are uncommon.
The fabricator and supplier Nucor Skyline shipped the casing by rail and truck in 75-foot sections. Harms needed a way to assemble them on site. “We set up a semi-automated shop to weld the sections quickly,” recalls Jason Hardell. “We talked to a few different welding equipment manufacturers early on and came up with this system.”
Two sections are placed on an automated roller assembly, joined, full penetration welded in several passes, and ultrasonic tested to verify strength. The completed full-length casing was trucked to the shoreline and shipped to the BG 55 barge for installation.
The welding system proved to be an effective alternative to workers doing the job by hand. “You’re doing a full penetration V-shaped weld on 1-inch casing,” says Rob Harms. “It’s a serious welding job.”
Specially Designed Conventional Tools
ECA and Harms chose conventional tooling for the BG 55 during the pre-bid phase. “We chose to drill with a lockable Kelly bar combined with BAUER tools including double-cut rock buckets and a cleanout bucket,” says ECA’s Gordian Ulrich. “For better guidance, verticality and production reasons, we designed and built these tools extra-long and equipped them with Betek bullet teeth.”
Drilling up to 240 feet with a telescoping four-section Kelly bar was no easy task. This 84-meter (275.5-foot) bar is custom-made for the BG 55. It is among the largest of the few that exist in the U.S. and the longest ECA has sold. “The telescopic Kelly bar is like a long asparagus-type bar; the longer you extend it, the more it tends to wobble,” says Ulrich. “When you crowd down on the bar the tip tends to take the path of least resistance below the casing, so putting the right tool on it and having well-trained operators are key factors in the drilling success.”
The project had a tough vertical tolerance spec of 1.5 percent. Harms purchased Kelly bar stabilizers Bauer had used on several other deep holes around the world, but the skill of its operators in combination with the specially tailored tools made them unnecessary. They operated within that tolerance starting with the first drilled shaft. Harms had no regrets because that kind of preparation beats shutting down the project for months while tooling gets manufactured.
Building the Foundation for Progress
Harms is on track to complete this roughly 4½-year project on schedule. It then passes the torch to the phase two contractor to construct the lift bridge and flanking spans superstructure, communications, and signal and overhead catenary work. Phase three sees rail traffic transfer to the new bridge and the demolition of the old bridge.
See more products and stories from the construction sector
“The drilling rig (BG 55) is really what’s driving the job,” Rob Harms says. “The shift from two 12-hour shifts to three 8-hour shifts really made a difference. It’s going really good.”
Building a foundation for a structure of this size and complexity is a challenge regardless of the construction method chosen. In the case of the Raritan River Bridge, Harms combined innovation, teamwork, pre-planning, vendor partnerships and the right equipment to make the project a success.