On Oct. 4, onlookers watched as a 12.5-foot-diameter Robbins Main Beam TBM completed its epic journey. The TBM, christened “Driller Mike” after local rapper and activist Killer Mike, overcame extremely hard rock conditions along a curving 8.0 kilometer (5.0 mile) tunnel to bolster the city of Atlanta’s water supply.
The new tunnel brings the Atlanta Water Supply Program one step closer to increasing the city’s water capacity to between 30 and 90 days depending on daily usage. “Our schedule for the project was very aggressive, but the project team stayed together to overcome issues related to the mining of the tunnel,” says Bob Huie, project director for the PC Russell JV, the construction manager at risk (CMAR) for the project.
The unique structure of the project team is credited with the overall project success despite challenges. “I’m proud of our team. They had obstacles and challenges and challenging ground, but they stuck together and didn’t give up, and they were successful. There was great leadership and supervision all around,” says Larry Weslowski, tunnel superintendent for the PC Russell JV.
The project is only the third large construction project in the U.S. to use the CMAR structure. The PC Construction/HJ Russell JV team was selected as the CMAR for the project, who then purchased the Robbins Main Beam TBM for the tunnel. The designer for the construction works including tunnel and shafts, JP2—consisting of Stantec, PRAD Group, Inc., and River 2 Tap—specified the hard rock TBM. Operation and assembly of the TBM was then sub-contracted to the Atkinson/Technique JV.
The robust TBM was assembled using onsite first time assembly (OFTA) at the massive Bellwood Quarry site with help from Robbins personnel. “The guys built everything per the specs to help with scheduling. It was a challenge, but there was no negativity during the process,” says Weslowski. Despite summer temperatures hitting 110 degrees Fahrenheit (43 degrees Celsius) and 100 percent humidity, the TBM was ready to launch by October 2016.
Hard granitic rock challenged the 19-inch disc cutters from the outset. “There was ground so hard that it would take eight hours to go 1.5 meters (5 feet). It was between 117 and 310 MPa (17,000 and 45,000 psi) UCS. The beginning of the job was tough,” says Weslowski, but he added that once the learning curve had been overcome, “they started breaking project records left and right towards the end. We got a best day of 38.4 meters (126 feett). Rates just kept increasing.”
Other challenges included groundwater encountered during tunneling. “We did encounter groundwater contamination that required remediation. This remediation work was completed successfully,” Huie says.
With tunneling complete, the USD $300 million project for the City of Atlanta’s Department of Watershed Management is on track to meet its scheduled overall completion date of September 2019. The project will turn the inactive Bellwood quarry into a 9.1 billion liter (2.4 billion gallon) raw water storage facility connecting with the Chattahoochee River and various water treatment facilities.