McCarthy
Building Companies Inc., one of the nation’s largest commercial construction
companies and a leading water treatment facility builder, recently began
construction of the Initial Expansion of the Groundwater Replenishment System (GWRS)
for the Orange County Water District (OCWD), which manages the large ground water
basin that underlies north and central Orange County
that provides most of the water for about 2.4 million citizens. Located at the
OCWD Advanced Water Purification Facility (AWPF) on Ward Street in Fountain
Valley, Calif., the $142.7 million
project will create an additional 31,000 acre-feet per year (AFY) of new water
supplies to serve north and central Orange
County. Once completed,
the AWFP’s total production will reach 103,000 AFY, enough water for 850,000
people.
A formal
groundbreaking event with local, county and state elected officials, water
retail agencies and representatives from the design firm and construction team
was held on Jan. 17, marking the start of the project.
“The GWRS
established the benchmark for international water projects and water reuse
technology,” says OCWD general manager, Mike Markus. “Most importantly, the
GWRS has provided a reliable, locally controlled source of water for Orange County
during a time when the availability of imported water is decreasing, while its
cost is increasing. We live in a naturally arid region. The GWRS Expansion will
provide us with the water supply reliability that we need, while creating
hundreds of local jobs that will benefit Orange County’s
economy through the development, construction and operation of the project. In
short, it’s the perfect project at the perfect time.”
The GWRS, a
joint project of OCWD and Orange County Sanitation District (OCSD), takes
highly treated wastewater that normally would have been discharged into the Pacific Ocean and purifies it through a three-step
process that includes microfiltration, reverse osmosis and ultraviolet light
with hydrogen peroxide. Thirty-five million gallons of near-distilled quality
GWRS water per day are pumped into injection wells where they serve as a
seawater intrusion barrier. Another 35 million gallons per day are pumped in a
13-mile long pipe to OCWD recharge basins in Anaheim, Calif.
The GWRS water then filters through sand and gravel to replenish the deep
aquifers of Orange
County’s ground water
basin, and ultimately becomes part of the drinking water supply.
Serving as
general contractor for the expansion, McCarthy will construct a 30-million-gallon-per-day
(MGD) treatment facility, expanding the 70 MGD GWRS that was completed in
2008. Parsons of Pasadena is
construction manager for the project, and Black and Veatch of Irvine is the
structural, civil, electrical and mechanical engineer.
The project
entails expansion of the existing microfiltration facility by constructing eight
new below-grade treatment basins and enlarging the existing basement facility.
Other work includes construction of a new 32,000-square-foot reverse-osmosis
building, the installation of five new ultraviolet light (UV) treatment trains
to match the existing systems, as well as retrofitting the existing post-treatment
systems to employ a new lime-feed system. McCarthy also will construct two
aboveground steel tanks; each is 215 feet in diameter with a height of 35 feet
and a capacity to hold 7.5 million gallons of water.
“The
project will be carefully executed in order to mitigate any disruptions to the
existing plant while conducting a complex facility expansion with significant
construction challenges,” says McCarthy project manager, Curtis Horner. “The
microfiltration facility is a very complicated water-bearing structure tucked
into an extremely tight footprint. This 30-foot deep structure is bordered on
all four sides just beyond the limits of construction by existing structures
and piping. The excavations and concrete durations alone will take
approximately 14 months to complete.”
The reverse-osmosis
(RO) building also provides project challenges, explains Horner. “The RO
facility is located in an area bordered by the existing facility, a substation,
a pumping area and another building. Furthermore, the structure will sit on
more than 200 piles with a long, extensive concrete scope, followed by
extensive mechanical work.”
The GWRS is
the largest advanced water treatment facility of its kind in the world, and has
garnered more than 35 regional, state and international awards, including the
prestigious American Society of Civil Engineers (ASCE) 2009 Outstanding Civil
Engineering Achievement Award for the year’s most outstanding national
engineering project, and the Stockholm 2008 Industry Award for the year’s most
outstanding international water project.
“We are
proud to be a part of this complex and vital project to mitigate the challenges
associated with an otherwise dwindling water supply in Orange County,”
says Mark Mardock, McCarthy executive vice president. It’s exciting to not
only be involved with an internationally
renowned project, but also helping to provide a environmentally responsible,
reliable and safe source of water, which is critical to the public health and
economy of Orange County.”
Construction
work is scheduled to complete in September 2014.