Contributed by American Piledriving Equipment’s Jimmy
Deemer:
U.S. Wick Drain Inc., a Leland, N.C.-based company, has just
completed the largest marine barge installation wick drain project that has
ever been done in the world. This project is part of the first phase of
construction for a new port facility at Craney
Island in Norfolk, Va. U.S. Wick Drain, under direction of
president Mark Palmatier, installed more than 12 million linear feet of wick
drains in six months using American Piledriving Equipment Inc.’s wick drain
installation machines. That’s six months with two rigs, 24 hours a day, six
days a week – a lot of wick drains. The longest wick drains were 150 feet
in length.
A drainage layer of sand was dumped in the proposed wick
drain area with hopper barges. The wicks will be placed and more sand dumped on
top of them. In order to place the wick drains in the correct locations on the
water, two barges had to be converted to have a grid all the way through the
decks of the barges using steel pipe from the top deck all the way through the
bottom. Each barge had a wick drain machine/rig on the deck. The barges
would be surveyed into position and secured, and then each machine would go
down the deck, installing a wick drain in each provided hole.
Once these wick drains are installed and pre-loaded, the
engineers predict they will have about 21 feet of settlement. These wicked
areas will support a series of dikes for the new Craney Island
port. If wick drains were not used, the dikes constantly would be settling, and
would have to be maintained at great cost.
Giant Wick Drain Project
Looking for a reprint of this article?
From high-res PDFs to custom plaques, order your copy today!