A large project was completed using a rotary sonic rig.
Huss Drilling Inc., Dade City, Fla., recently
completed a large project using its new Geoprobe 8140DT rotary sonic rig in the
Fort Walton Beach area of Florida.
According company owner Ben Huss, the difficult task encompassing the project
was completing most of the work inside several warehouse buildings. “The
entrances were tight, yet the compact nature of the 8140DT allowed us easy
access to the various rooms within the building,” explains Huss. The rig was
fitted with an exhaust piping system that pulled the fumes from the engine and
discharged them outside the building. A blower also was installed, which aided
in pulling out the exhaust fumes. Even though outside temperatures remained
cool, large shop fans were placed about the work site for added ventilation.
The low overhead clearance of the sonic rig provided the accessibility to
perform all of the work that needed to be done – in spite of being inside a building
with a rather low clearance.
During the month-long drilling event, the seasoned crew of Kent Fowler and Tony
Hudson performed continuous soil sampling and ground water sampling, and
installed monitoring wells 100 feet below land surface. The soil sampling was
performed using a 4-inch core barrel with a specially adapted bit to capture
the loose flowing sands encountered on site. Ground water samples were obtained
by installing temporary screens, and then retracting the sample casing at
specific intervals. The monitoring wells were completed inside the various
sizes of override casings, depending upon the well diameters. More than 30
wells were installed during the project, many of which were located inside
warehouse buildings.
Onsite engineers were extremely pleased with the performance of the Geoprobe
8140DT. “The rig performed without any lost time due to breakdowns, allowing us
to complete the anticipated five-week job in one month,” Huss adds. “We were able
to provide our client the information necessary to assess the contamination
levels, and place the monitoring wells in strategic locations, while saving
significant costs associated with the typical disposal of cuttings.”
ND
On the Job: Tight Conditions Challenge Sampling Project
Looking for a reprint of this article?
From high-res PDFs to custom plaques, order your copy today!