One such source for clean renewable energy is wind. Turbine generators, which are driven by wind energy, are being built where there is a sufficient supply to drive them economically. One such area is near Lawton, Okla., in an area locally called the Slick Hills. The project completed there is called Blue Canyon Wind Farm Phase Five, and the job was handled by Dykon Blasting Corp. of Tulsa, Okla.
Energy prices are high and
getting higher all the time. Demand for energy is ever-growing, and
availability declines daily. As time goes on, fossil fuel supplies are
continually depleted and not being replenished. Some day in the future, the
vast supplies of this precious resource will be gone, and we will be forced to
turn to other sources for energy or return to the Stone
Age.
In addition to the problem of depleting resources, we are faced with the
reality of the byproducts of fossil fuel consumption. Pollution, smog and
increasing levels of carbon dioxide are released into the atmosphere. The
importance of developing clean renewable energy is escalating in proportion to the
growing need for energy and clean air.
One such source for clean renewable energy is wind. Turbine generators, which
are driven by wind energy, are being built where there is a sufficient supply
to drive them economically. One such area is near Lawton, Okla.,
in an area locally called the Slick Hills. The project completed there is
called Blue Canyon Wind Farm Phase Five, and the job was handled by Dykon
Blasting Corp. of Tulsa, Okla.
The wind turbines are manufactured by General Electric, and each turbine has a
1.5-megawatt capacity at full output, and will produce enough power to light
roughly 500 homes. Phase five involved the construction of 66 wind turbine
towers. All of the wind turbines on this project were constructed in areas
where rock had to be excavated for the foundations. There were two
different types of foundations utilized for this project. In areas of competent
rock, 19-foot diameter sockets, 20 feet deep were used. In areas of less
competent material, large spread footings were constructed as bases to support
the towers.
But before any wind turbines can be constructed, there must be suitable roads
for getting the large equipment necessary to erect these towers in each of
their locations. This project had more than 19 miles of road in order to access
all 66 tower sites. The road-building crews were the first ones to work on the
construction process of the project.
D8 Caterpillar dozers began scraping roadways into the landscape. The wind
generators were constructed on the highest areas of the Slick Hills, where
there was little to no dirt on top of solid rock. The high spots had to be
blasted off for use to fill the low spots, thus the building of roads at a
grade suitable for the massive cranes and other construction equipment that
would be driven to each site.
The construction process started as soon as roads suitable for access were
ready. Close on the heels of the dozers, graders, compactors, excavators, haul
trucks and blasters were the excavating crews responsible for installing the
foundations for the towers. All of these foundations had to be drilled and
blasted before they could be excavated. The blasting of these foundations was
accomplished concurrent with the road building process. As soon as the roads
were suitable for blasting crew access, the foundations were drilled and
shot.
As soon as the foundations were excavated, the rebar crews moved in and started
building the large reinforcing cages for the concrete foundations. Soon
afterward, the concrete was poured for the foundations. The demand for concrete
was so great that two concrete batch plants were erected onsite to meet the
demand.
While the concrete was being poured, tower sections and generator components
were being moved to each location ahead of time. As soon as the concrete
foundations had cured enough to support the load of the towers, the erection
process for those began. The first erection crew assembled the blades onto the
central hub, set the generator nacelle into place and erected the bottom two of
three tower sections onto the foundations.
The second tower construction crew then came with a 450-ton crawler crane, and
erected the top section of the tower, placed the generator nacelle, and hung
the rotor with the blades attached in a single unit.
While all this was all taking place, electrical contractors were hooking up the
transformers and other electrical components, and building the gathering system
that would carry all of the generated electricity to a single sub-station,
where it would then be sent out for public sale and
consumption.
All of these operations started and were in full progress before the blasting
and road construction was finished. This project required a remarkable
feat of coordination to keep all of the necessary crafts moving efficiently and
without interruption. All of this activity and construction traffic was
taking place on a single one-lane road about 25 feet wide.
From start to finish, the blasting for all of the roads and all foundations was
accomplished within the required timeframe. A total of 66 foundations and
286,000 square feet of roadway had been drilled and shot in about nine
weeks.
ND