The existing south access road to San Francisco’s Golden Gate Bridge, known as Doyle Drive or Route 101, is structurally and seismically unsafe, and requires replacement. Built in 1936, Doyle Drive has reached the end of its serviceable life. The foundations for the new South Viaduct Bridge presented quite a challenge to Malcolm Drilling Co. due to the requirement for deep, large-diameter drilled shafts installed adjacent to historic landmarks. Drilled shafts with 12-foot diameters were constructed to depth of approximately 200 feet.
The
existing south access road to San Francisco’s Golden Gate Bridge, known as
Doyle Drive or Route 101, is structurally and seismically unsafe, and requires
replacement. Built in 1936, Doyle
Drive has reached the end of its serviceable life.
The project is located within the Presidio of San Francisco, part of the Golden
Gate Recreation Area, and is part of the primary north-south highway and
transit linkage through San Francisco.
The foundations for the new South
Viaduct Bridge
presented quite a challenge to Malcolm Drilling Co. due to the requirement for
deep, large-diameter drilled shafts installed adjacent to historic landmarks.
Drilled shafts with 12-foot diameters were constructed to depth of
approximately 200 feet.
The viaduct bents are founded on 12-foot and 8.5-foot-diameter drilled shafts,
while abutments and retaining walls are installed on smaller-diameter drilled
foundations. The bridge design required a single drilled shaft below each
column. The 12-foot-diameter drilled shafts required permanent steel casing to
be installed up to 160-foot depth under extremely strict vibration limitations.
Malcolm employed the world’s largest oscillator to advance the casing without
inducing ground vibrations, while a spherical grab excavated overburden soils
within the casing. A BG40 rotary drilling rig was used to bore an
11.5-foot-diameter rock socket, which was drilled below the permanent casing
tip. The seismic loads resulted in a very dense reinforcement configuration
with individual pile cages weighing up to 150 tons. A custom-designed tipping
frame and unique suspension systems were required to handle and splice these
exceptionally long and heavy rebar cages.
Conditions at the site comprised of alluvial soils, extending to depths up to
160 feet, overlying bedrock of the Franciscan Complex. All shafts have been
designed to develop their load-bearing capacity both in end-bearing and
side-friction in the bedrock only. The Franciscan Complex is composed of
sandstone, shale, limestone, chert, serpentine and greywacke – mixed in a
seemingly chaotic manner. Engineering properties of the Franciscan vary
significantly within limited vertical and horizontal intervals. Ground water was
encountered between 20 feet and 60 feet below working
grade.
The shaft integrity was tested using Gamma-Gamma and CSL test methods, while
visual inspection by the Mini SID camera ensured a clean base that was required
for end-bearing capacity. Malcolm Drilling employed synthetic slurry to
stabilize the open rock socket to ensure compliance with the specifications
through carefully controlled slurry exchange procedures. The concrete mix
design was developed with a special emphasis on workability, which was needed
for an extended period for the tremie concrete placement operation. The mix had
the characteristics of self-consolidating concrete (SCC), with 50 percent of
the Portland cement replaced by slag and fly ash.
From very humble beginnings, Malcolm Drilling has experienced growth over the
past 4.5 decades to its present position as a preeminent specialty foundation
contractor in the world.
ND
On the Job: Malcolm Meets Viaduct Challenge
Looking for a reprint of this article?
From high-res PDFs to custom plaques, order your copy today!